Tarmac complete innovate runway resurfacing project

28.08.07

Runway resurfacing is a unique sector within the construction industry and one that is evolving fast. The boom in low-cost air travel is putting additional demands on contractors and materials suppliers, who are responding with new ideas - as a recent project at Liverpool Airport shows.

Tarmac has just finished its largest airfield job to date at the airport, a £10m contract for resurfacing the runway, taxiways and apron. There have been 'firsts' throughout the project, including first use of innovative materials at an airport and unprecedented quantities of work carried out in short shifts. Both have resulted from pressures now typical at UK airports.

Demand for runway availability at Liverpool Airport meant only 6 hours were available each night for the work, which made laying a total of 90,000t of material far more of a challenge. Maximising asphalt production and laying within the hours available led to selection and first use of foam mix recycled asphalt at an airport.

The recycled asphalt could be laid in one pass in 7.5m-wide strips along the whole 2.4km length of the runway's shoulders. Tarmac's project manager Andy Reynolds said: 'This allowed the shoulders to be used for construction traffic. Vehicles were run on the shoulders while we reconstructed the main runway across the remaining 45m width, cutting from the programme.'

Tarmac specified a very strong pavement for the runway, consisting of a 100mm layer of dense macadam base course, a 60mm Marshall Asphalt binder course and a 50mm Marshall surface. Each layer was bonded together and fixed to the runway's concrete base with Nyclean bond coat - effectively creating a single pavement layer.

Bonding the upper layers is normal practice, but creating a strong bond with a concrete base is an advance of bondcoat technology, which has also been exported from highway to runway surfacing. Mr. Reynolds said: 'I've not seen anything like it. When we went in to get cores during trials of the pavement, it was stuck solid.'

Despite its best efforts, Tarmac needed 6 months to complete its work, partly because it had to be done in the airport's quiet season. Bad weather stopped work on 22 nights, and a normal night for the 100-strong team involved gearing up in time to move onto the runway at midnight with planers, pavers, rollers, tractairs, sweepers, a bondcoat tanker and spare plant for every item in use.

Planing was followed by bondcoat, laying of the macadam base, bondcoat again and then the Marshall binder course. The team would clear the runway so it could be fully inspected before the first flights at 06:30, which landed on a new pavement course.

Add to: del.icio.us | Digg it | Newsvine | NowPublic | Reddit

To book liverpool airport hotel or liverpool airport car parking at the lowest price, click on these links to two great liverpool airport parking and liverpool airport hotel price comparison pages.

 

More Coming Soon
Liverpool Airport News
Local Attractions

 
 
Liverpool Airport Services
 

Liverpool Airport Parking
Liverpool Airport Hotels
Liverpool Airport Lounge
Foreign Currency Liverpool Airport
Resources

 
 
Other Airport Guides

Belfast Airport
Birmingham Airport
Bristol Airport
Cardiff Airport
East Midlands Airport
Edinburgh Airport
Gatwick Airport
Glasgow Airport
Heathrow Airport
Luton Airport
Manchester Airport
Newcastle Airport
Stansted Airport
World Airports
UK Airport News

 
Useful Websites
Liverpool Airport Hotels
Liverpool Airport Parking
 

contact us : about us : privacy : site map

© TMC Ltd